identify the three goals of a project. what does it mean for a project to be "overdetermined?"

(This postal service contains chapter links. Read my full disclosure.)

This is a invitee article by Dr Mike Clayton from OnlinePMCourses.com.

We all know that defining your project well is the foundation of good projection management. Without it, you're managing a mess. Goals, objectives and telescopic count for a lot. In this article, we'll discuss how to become those defined.

In this article:

  • The 3 things that make a solid projection definition
  • The showtime problem is goals and objectives
    • Goals
    • Objectives
    • Scope
    • The biggest mistake in scoping a project
  • There'due south more

There's ane thing I've learned in preparation many thousands of project managers. This one topic seems to hold the biggest light-bulb moments.

Because for some people, getting a clear project definition is like sculpting a heap of jelly. That's jello to my United states of america cousins.

You often take an baggy prepare of wants and desires, hopes, dreams and needs. Each subset is championed past a unlike stakeholder. Each stakeholder has their own style and way of expressing their priorities. And, it gets more than complicated still. Your stakeholders have different levels of authority and influence.

And there is one more complicating cistron. Terminology.

There's a lot of jargon effectually project definition. In fact, this is the stage in the projection lifecycle with the almost different names:

  • Definition
  • Start-up
  • Initiation
  • Concept
  • Scoping
  • Assay
  • Proposal

The 3 things that brand a solid project definition

Let's cut through the clutter.

The cadre of a solid project definition is iii things:

  1. Goal
  2. Objectives
  3. Telescopic

If you tin understand these and can elicit each one clearly from your stakeholders, you'll be in great shape.

By the way, that's not always easy. In fact, I consider scoping to be the hardest role of project management. Which is all the more reason to understand it well.

Dr. Mike Clayton quote

The starting time trouble is goals and objectives

This is a problem, because distinguishing them is not always easy. Indeed, some people talk of 'goalsandobjectives' almost as one give-and-take.

So permit me brand information technology very like shooting fish in a barrel to carve up the 2 ideas.

Goals

A goal is what you desire. It answers the get-go question you should put to your boss, your projection sponsor, or your customer:

'What practice you desire?'

You may likewise need to consult key stakeholders. When you have achieved a consensus about your project goal is, it's time to move onto their objectives.

Objectives

Objectives gear up out what's important most how you lot achieve your goal. They articulate what your stakeholders intendance about, and their criteria for full success. Again, commencement with your leading stakeholder: your boss, your project sponsor, or your client. So consult others. Ask them:

'How do you want the goal delivered?'

Typically, people will answer in terms of the triple constraint of:

  1. Time – they will have preferred deadlines. They may accept required deadlines.
  2. Cost – they may desire y'all to go on within a certain budget.
  3. Quality – they may prepare you specific quality standards to see.

Over again, information technology'southward typical to find that about stakeholders try to tie yous down to fixing all three. The mutual project manager'due south refrain is:

'Time, cost, quality: selection two'

That'south non strictly necessary. As long as the three are consistent, it's fine in principle. To be OK in practice, you too need to have enough contingency in each of them, to adapt the level of risk in your project.

Equally a proxy for risk at this stage, consider a combination of:

  • scale
  • novelty
  • complexity
  • priority.

Read next: The Complete Guide to Project Risk Management

Scope

Your project scope sets out the breadth and depth of your appetite for your project. Or, more correctly, your stakeholders' ambitions.

It answers the question:

'How much of it do you want?'

At that place are 2 approaches to scoping. They depend on whether your project direction is rooted in the Great britain or US. Neither is amend, but I guess nosotros all have a preference.

In the US, the telescopic of your project is the amount and range of products your project will evangelize. Once yous have defined that, the secondary step is to piece of work out the activities you'll demand, to deliver them.

In the UK, project managers talk of the scope of piece of work for your project. The telescopic is thus the range of activities the project will embrace. Then, the secondary step is to list the deliverables those activities will produce.

The biggest mistake in scoping a project

Whichever approach you have, there is one further affair you lot must do. The common mistake is to ready out your scope clearly and stop.

What happens and so is stakeholders see that scope, interpret the words liberally, and presume they mean more they do. The phrase you'll hear is:

'While you lot're doing that, could y'all just… ?'

You must counter this tendency towards telescopic pitter-patter. If y'all don't, it's a recipe for delay, cost over-runs, errors and defects, and stress. And the mode you exercise it is to look at the boundary effectually your scope.

causes of scope creep
The peak causes of scope creep on projects

Consider every border case. And and then explicitly document what is not included in each telescopic item. This is your listing of project exclusions.

Get your telescopic exclusions signed-off as part of your full argument of scope, which should as well include whatever project assumptions.

That way, when someone asks: 'could yous only…?' You can answer:

'I really wish I could. Merely I can't. See here… It's on the listing of things my dominate, sponsor, client says are excluded from the projection. Sorry.'

There'south more

Of course, in that location's lots more to project definition.

On my own website, at OnlinePMCourses.com, y'all'll find an extended article. And one of our newest programs is The Projection Director'due south Project Definition Kit.

Merely here's 1 matter I've learned. Goal, Objectives, and Scope are the 20 per cent of project definition that deliver 80 per cent of value.

These three key elements are about accuracy. Everything else is about precision. Get these three right, and yous'll be striking the centre of your projection target. Everything else just clusters your aim more than tightly.

About the Author: Dr Mike Clayton is a Project Manager. He has also trained over six,500 projection managers, coached, spoken and written extensively. He has five books on projection management with Pearson, Wiley and Macmillan. Mike is the founder of Online PM Courses.com, which provides video-based online training for new and mid-level projection managers as well as the costless PM introductory course Project Management Fundamentals.

Pin for later reading:

The 3 most important things that define your project

mimsundkey.blogspot.com

Source: https://rebelsguidetopm.com/3-important-things-that-define-your-project/